| File Number | 3309 |
|---|---|
| Application Type | PU |
| Status | |
| RFI Date | |
| Application Submitted Date | 2022-11-30 |
| Application Fee Paid Date | |
| License Expiration Date | 2073-02-07 |
| Notes | |
| Applicant | El Paso Electric |
| Primary Contact | Claudia Hunter |
| Engineer | Jose Barron | Surveyor | Christian Wegmann |
| Proposed Use of District Property | three phase overhead crossing |
| District Property Crossing | Mesa Drain @ Old Hueco Tanks |
| Document | Document Title | Note | Relevant Status |
|---|
| File Closed | 2024-09-11 |
|---|---|
| Construction Completed | 2023-08-28 |
| Board Approved | 2023-03-03 |
| Application Submitted | 2022-12-16 |
| Engineering Drawing Submitted | 2022-11-30 |
| Administrative Fee Paid | 2022-11-30 |
| Survey Submitted | 2022-11-30 |